Our current lead times on different product ranges are as follows. Glazing Vision UK only. All times are from receipt of payment in accordance with agreed payment terms.

FlushGlaze Standard: 4 Weeks

FlushGlaze with alternate colour: 6 Weeks

Walk on FlushGlaze: 6 Weeks

Circular FlushGlaze: 7 Weeks

FlushGlaze with VisionVent: 6 Weeks

VisionVent: 4 Weeks

Skyline: 4 Weeks

Octagonal Skyline: 5 Weeks

SKYGLIDE (Flat and Pyramid) opening rooflight: 6-7 weeks from signed confirmation and deposit, Size limitations will apply for this unit.

Sliding Over Roof Standard Rooflight: 8 weeks from signed confirmation and deposit, Size limitations will apply for this unit.

Sliding Over Fixed Standard Rooflight: 8 weeks from signed confirmation and deposit, Size limitations will apply for this unit.

3 Wall Mounted Box Standard Rooflight: 8-10 weeks from signed confirmation and deposit, Size limitations will apply for this unit.

Free Standing Box Standard Rooflight: 10-12 weeks from signed confirmation and deposit, Size limitations will apply for this unit.  

For official quotations please allow 1-5 days turnaround